4.1.1---P3---Back-Up---QuickProof_AusCon_2019_NOV_WA_107_F

Roy Hill Master Service Agreement

Client: Roy Hill
Location: Roy Hill Minesite, Pilbara Region WA
Duration: November 2016 – December 2019

Inoteq were initially contracted by Roy Hill to install and commission a Turkeys Nest at the Roy Hill mine site. Inoteq were subsequently awarded a dewatering MSA to install upcoming dewatering requirements, along with maintaining existing pipelines and bore pump infrastructure.

Milestone projects which were completed during this timeframe include, but not limited to: Zulu 9 Borefields; Process water dam remediation works (including supply and installation of DN1000 perimeter manifolds); TSF pipe upgrade and many smaller packages of borefield and pipeline installations.

Inoteq had its contract renewed in December 2018 following many successful projects with Roy Hill.