4.1.1---P2.-Wakathuni-Tank-Upgrade_F2

Wakathuni Tank Upgrade

Site location: Wakathuni Community
Client: Department of Communities
Duration: April 2019 – October 2019

Inoteq were contracted by the Department of Communities to design, supply and install a new ground water tank, pump Sstation and associated pipework for the town water supply at the Wakathuni Community in the Pilbara.

The project comprised a 150kL above ground storage tank, a duty / standby pump station, new electrical switchboard to interface with the new and existing infrastructure, buried and above ground ABS pipework, new water storage facility compound and the associated earthworks required to complete the scope.

Commissioning of the new facility was completed along with integration into the existing water storage / transfer facility whilst maintaining town water supply for the duration of the project.

Inoteq completed the project on time with no safety issues or disruption to the local community.